Skip to main content

WIND ENERGY

A Telehandler Lifting Beyond Its Rated Limit

On a wind farm construction project in Finland, our safety officer spotted a telehandler being used well outside its capacity, and stopped the job before the load became a serious incident.

Wind farm construction site in Finland where a Coyle Group safety officer identified a telehandler overload
Industry
Wind Energy
Location
Finland
Year
2017
Client
Wind farm developer (anonymised)
Coyle role
On-site Safety Officer

The challenge

The Wrong Tool For The Job

In 2017 we placed a Coyle Group safety officer on a wind energy construction project in Finland. While the team was placing and removing ballast from the main installation crane, he noticed that a telehandler was being used to do the lifting, and that the load looked heavier than the machine was rated for.

The telehandler was carrying 12.5 tonnes. The duty chart set a maximum working load limit of 12 tonnes. He brought the issue to the crane company and site management straight away. When the method was allowed to continue, the telehandler tipped forward as the load became dynamic, exactly the failure the rating exists to prevent.

What we found

Speed Before Safety

Once we stopped the work and held a time-out for safety, the root cause was clear. There was a rigging crane on site that had originally been planned to carry out this task. The decision had been taken to use the telehandler instead, to speed the operation up, which meant disregarding the manufacturer's operating instructions.

The fact that the first warning had not been heeded pointed to a wider issue: a lack of safety culture that sat with both the site team and the contracted crane company. This was an organisational failing, not a one-off mistake, and it needed urgent attention.

What we did

Putting Safety First

Our consultant stopped the work and held a time-out for safety, the same disciplined accident investigation approach we bring to every site. With the team, he re-established the original plan of using the rigging crane for the lift, so the task went ahead within safe limits.

Just as important, the intervention reset how the team thought about the work. As the safety culture improved, the client issued a Safety Alert company-wide to emphasise the risk of using machinery in this way. By fully buying into carrying out the job safely, the project finished on time and without any further incident of this kind.

The Outcome On This Project

12.5
Load lifted by the telehandler
Against a 12te working load limit on the duty chart
0
Further incidents of this kind
After the rigging crane plan was re-established
1
Company-wide Safety Alert issued
The client shared the risk across every site

Related case studies

More From The Same Vertical

CMIOSH · The Coyle Approach · 48 hours

Get The Same Chartered Eyes On Your Wind Project

We place degree-qualified safety officers on wind energy sites within 48 hours, backed by our chartered founder. Tell us about your project and we will match the right officer.

Discuss your requirements